Wednesday 16 January 2013

Progress report on St Martins Road and Sandplace Road works

Progress report on St Martins Road and Sandplace Road works

Progress update - 15 January 2013
St Martins Hill Looe
Slope failure
Programme of works
Lower section of failed slope Higher section showing
signs of imminent failure
CORMAC
Solutions Ltd and CORMAC
Contracting Ltd, Head Office, Castle Canyke Road,
Bodmin, Cornwall PL31 1DZ
Tel: 0300 1234 222
Email: customerrelations@cormacltd.co.uk
www.cornwall.gov.uk/cormac
32351 01/13
Post Christmas works
2 January to 4 February
Rock anchoring higher section
Relocation of WPD pole and overhead line to lower slip area
Excavation of lower slip and adjacent substandard wall (towards
junction area)
Rock anchoring lower slip failure
Spray concreting lower slip failure
4 February to 4 March
Micro piling in carriageway from higher section to lower slip area
Foundation for stone walling to lower section
Stonework to lower section
4 March to 28 March
Finish stonework
Kerbing
Resurface St Martins nearside carriageway
If you wish to report a problem please telephone our highways staff
who will be able to deal with your enquiry on 0300 1234 222.
Following a significant failure of the embankment
approximately 20 metres from the junction of
St Martins Hill and Sandplace Road that
undermined sections of the carriageway, Cornwall
Council took the decision to close Sandplace
Road and operate traffic lights on St Martins Hill.
Higher Section of St Martins Hill (Stage 1)
A series of micro piles will be installed in the affected area that will provide
permanent stability to the affected ground.
Higher Section of St Martins Hill (Stage 2)
Tension Crack
Micro
Rock
Soil
Remove any
loose surface
Parapet
Higher Section of St Martins Hill (Stage 1)
Work carried out to date
The tree and vegetation clearance of the entire embankment
area was completed at the beginning of January and the first
coat of spray concrete applied to the lower slip area.
During January will see the spray concreting process continue
with further coats being applied with steel mesh to form a
robust concrete repair system. Once this is completed and
adequately cured, we hope to be able to start soil nailing the
lower slip area, weather permitting.
The post Christmas works have continued with the micro piling downhill
from the upper section (20no).
Western Power Distribution completed the overhead electric cable and
pole diversion works.
The lower slip area and adjacent failing wall was also trimmed/excavated
in preparation for spray concreting, and the recent slip over Christmas
was cleared from Sandplace Road.
Our designers are working on a design solution for the upper
slip area which has been complicated by the recent additional
landslip which has undermined the concrete edge beam
along St Martins Hill.
We will be carrying out further inspections of the cracking
along Sandplace Road this week to assess what further works
are required.
At present all the works are on programme as initially advised.

1 comment: